Dock 21 Renovation In Ashdod Old Port Project

Following the company’s success in the national project of the New Southern Port in
Ashdod, DAKAR company was called to the renovation of Dock 21 in the old Ashdod port.
Usually dock renovation work is varied and even more complex than building a new dock.
Prior to the construction work, extensive dismantling work is needed, which includes cutting
old tenonings and drilling in crumbling concrete. After the first stage, there is a need to
stabilize and strengthen the dock through concrete castings and installation of steel locks.
Only then the work of extension begins, which included installing and cutting tenonings,
installing a Cathodic protection, stabilizing the ground and more.
The work was carried out combined with a few sources as: The Chinese PMEC company,
Israel Ports company and the Port of Ashdod.The work is complex and challenging, but we
are happy to provide the best service in accordance with the many and stringent quality and
safety requirements.